Legal Opinion

Poly-Flex Construction, Inc. v. Neyer, Tiseo & Hindo, Ltd.

District Court, W.D. Michigan

Decided October 6, 2008No. 1:07-cv-1090PublishedCited by 6 opinions

1Opinion of the Court

Opinion and Order

PAUL L. MALONEY, Chief Judge.

Granting the Defendant’s Motion to Dismiss the Complaint for Failure to State a Claim; Determining that the Complaint is Barred by the Professional-Malpractice Limitations Period; Terminating the Case

The defendant moved to dismiss the complaint for failure to state a claim. The motion was fully briefed, and the court heard oral argument on September 4, 2008. Pursuant to the court’s September 5, 2008 order, the parties submitted supplemental briefs as to whether PFC’s breach-of-contract and contractual-indemnification claims (counts one and three)…

2Cases cited78 opinions

  1. Bell Atlantic Corp. v. TwomblySupreme Court of the United States · 2007
  2. Erickson v. PardusSupreme Court of the United States · 2007
  3. Thomas v. ArnSupreme Court of the United States · 1986
  4. Arbaugh v. Y & H Corp.Supreme Court of the United States · 2006
  5. United States v. RaddatzSupreme Court of the United States · 1980

73 more not listed; retrieve them via the Exa API.

3Cited by6 opinions

  1. JDC MANAGEMENT, LLC v. ReichDistrict Court, W.D. Michigan · 2009
  2. Caron v. Cranbrook Educational CommunityMichigan Court of Appeals · 2012
  3. Lakeland Regional Health System v. Walgreens Health Initiatives, Inc.District Court, W.D. Michigan · 2009
  4. Dematic Corp. v. International Union, United Automobile, Aerospace & Agricultural Implement Workers of AmericaDistrict Court, W.D. Michigan · 2009
  5. Poly-Flex Construction, Inc. v. Neyer, Tiseo & Hindo, Ltd.District Court, W.D. Michigan · 2009

1 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API