Charlotte Farm & Mills appeals the environmental court’s order concluding that the zoning board of adjustment (ZBA) of the Town of Charlotte, and hence the environmental court, had jurisdiction to review a decision by the Town’s zoning administrator as to whether Charlotte Farm’s activities exceeded the scope of its zoning permit. We affirm. *
The material facts are not in dispute. In January 1998, Charlotte Farm submitted an application for a zoning permit to the Town’s zoning administrator. On its face, the application sought approval for an “agricultural operation” and “forestry” on a…
2Cases cited6 opinions
- In Re KostenblattSupreme Court of Vermont · 1994
- Petition of FairchildSupreme Court of Vermont · 1992
- Wesco, Inc. v. City of MontpelierSupreme Court of Vermont · 1999
- Kpc Corporation v. the Book Press, Inc.Supreme Court of Vermont · 1993
- In Re Appeal of SardiSupreme Court of Vermont · 2000
1 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- In Re Appeal of HigniteSupreme Court of Vermont · 2003
- Brooks v. Town of CharlotteVermont Superior Court · 2004
- Feeley Construction PermitsVermont Superior Court · 2010
- Marckres Zoning Permit 24-09 - Decision on MotionVermont Superior Court · 2026
- Moore Accessory Structure PermitVermont Superior Court · 2010
2 more not listed; retrieve them via the Exa API.