Newbanks v. Ash Grove Lime & Portland Cement Co.
Supreme Court of Kansas
1Opinion of the Court
The opinion of the court was delivered by
Harvey, J.:
This is an action in damages alleged to have resulted from the breach of a parol contract of employment for personal services. The trial court sustained a demurrer to plaintiff’s evidence, and he has appealed.
The legal question presented is whether the case is controlled by the statute of frauds (R. S. 33-106). In other words, was the parol contract relied upon one which could not be performed within a year?
In that portion of the petition necessary to be considered on this point it is alleged, in substance, that on May 27, 1926, plaintiff…
2Cases cited10 opinions
- Heery v. ReedSupreme Court of Kansas · 1909
- Osborne v. KimballSupreme Court of Kansas · 1889
- Pierson v. Kingman Milling Co.Supreme Court of Kansas · 1914
- Wolf v. DozerSupreme Court of Kansas · 1879
- Aiken v. NogleSupreme Court of Kansas · 1891
5 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Allen v. MoyleIdaho Supreme Court · 1961
- Manning v. Woods, Inc.Supreme Court of Kansas · 1960