Campbell v. Lodge No. 99, Ancient Free & Accepted Masons
Supreme Court of Kansas
Error from Sedgwick district court; William E. Stanley, judge pro tem.
1Opinion of the Court
The opinion of the court was delivered by
Porter, J.:
This action was brought by the Campbell Heating Company, á partnership, to recover the 'price of a heating plant placed in the building of defendants in error under a written contract. The answer set up (1) a general denial, (2) a breach of warranty, and (8) a subsequent oral contract between the parties, made after the plant was installed and found to be defective, by which plaintiffs agreed that if they were allowed to make certain alterations in the building and plant they would remove the plant provided it did not work satisfactorily and…
2Cases cited3 opinions
- Furneaux v. EsterlySupreme Court of Kansas · 1887
- Aultman & Taylor Machinery Co v. WierSupreme Court of Kansas · 1903
- Phelps & Bigelow Windmill Co. v. PiercySupreme Court of Kansas · 1889
3Cited by2 opinions
- Hickman v. RichardsonSupreme Court of Kansas · 1914
- Hull v. Prairie Queen Manufacturing Co.Supreme Court of Kansas · 1914