In Re Pilgrim Partnership
Supreme Court of Vermont
1Opinion of the CourtMorse, J.
Pilgrim Partnership appeals an order of the Environmental Board remanding Pilgrim’s Act 250 land use permit application to the District Commission. On remand the Board required Pilgrim to submit a revised plan with appellee, A.G. Anderson, Inc., as a co-applicant. The Board forbade Pilgrim from using a roadway to its warehouse until the Commission approved a revised plan pursuant to 10 V.S.A. § 6086(a)(5) (criterion 5). We affirm the remand but clarify that Pilgrim may show alternative means of compliance with criterion 5.
In 1986, Pilgrim acquired a lot and warehouse in Waterbury, Vermont. A…
2Cases cited3 opinions
- In Re Juster AssociatesSupreme Court of Vermont · 1978
- Application of Great Eastern Building Company, Inc.Supreme Court of Vermont · 1974
- In Re R.E. Tucker, Inc.Supreme Court of Vermont · 1988
3Cited by25 opinions
- In Re AudetSupreme Court of Vermont · 2004
- Madowitz v. Woods at Killington Owners' Ass'nSupreme Court of Vermont · 2010
- In re Costco Stormwater Dishcharge Permit, Costco Final Plat & Site Plan, Costco Act 250 Land Use Permit, Wetlands, Reclassification (R.L. Vallee, Inc. and Timberlake Associates LLP, Appellants)Supreme Court of Vermont · 2016
- In Re CVPS/Verizon Act 250 Land Use Permit Numbers 7C1252 & 7C0677-2Supreme Court of Vermont · 2009
- JIPAC, NV v. SilasSupreme Court of Vermont · 2002
20 more not listed; retrieve them via the Exa API.