Plaintiff sues for the value of extra-work which he alleges he was required! to do in completing a construction contract. This work he asserts he was not required to do by the terms of the contract.

In April 1956 plaintiff entered into a contract for the construction of facilities at Ozona, Texas, consisting of 12 buildings and utilities.

The standard form contract with certain additions contained certain provisions which are set out in detail in findings 1, 2, and 3. The main issue turns upon whether the contract required the painting of the interior walls of masonry. The…

2Cases cited1 opinion

  1. Garrison v. United StatesSupreme Court of the United States · 1869

3Cited by15 opinions

  1. Hol-Gar Manufacturing Corp. v. The United StatesUnited States Court of Claims · 1965
  2. WPC Enterprises, Inc. v. United StatesUnited States Court of Claims · 1963
  3. Blount Brothers Construction Company v. The United StatesUnited States Court of Claims · 1965
  4. Stein Bros. Mfg. Co. v. United StatesUnited States Court of Claims · 1963
  5. Kaiser Industries Corporation v. The United StatesUnited States Court of Claims · 1965

10 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API