U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.

Supreme Court of South Carolina

Decided January 20, 1997No. 24551PublishedCited by 19 opinions

1Opinion of the Court

WALLER, Justice:

The following question has been certified to this Court by the United States District Court for the District of South Carolina:

Under the facts of this case, what exceptions, if any, to an unambiguous no-damages-for-delay clause in a construction contract would the South Carolina Supreme Court recognize?

FACTS

Metric, general contractor for construction of a new federal prison in Estill, S.C., hired Williams Electric Company as the major electrical subcontractor. The contract, written by Metric, contains the following no-damages-for-delay clause:

7. Extensions of Time_ In the…

2Cases cited25 opinions

  1. Corinno Civetta Construction Corp. v. City of New YorkNew York Court of Appeals · 1986
  2. C.A.N. Enterprises, Inc. v. South Carolina Health & Human Services Finance CommissionSupreme Court of South Carolina · 1988
  3. Marsch v. Southern New England RailroadMassachusetts Supreme Judicial Court · 1918
  4. J&B Steel Contractors, Inc. v. C. Iber & Sons, Inc.Illinois Supreme Court · 1994
  5. Jensen Construction Co. v. Dallas County, Texas Court of Appeals, 5th District (Dallas)1996

20 more not listed; retrieve them via the Exa API.

3Cited by19 opinions

  1. Zachry Construction Corporation v. Port of Houston Authority of Harris County, TexasTexas Supreme Court · 2014
  2. Tupelo Redevelopment Agency v. Gray Corp.Mississippi Supreme Court · 2007
  3. J.A. Jones Construction Co. v. Lehrer McGovern Bovis, Inc.Nevada Supreme Court · 2004
  4. Miss. Transp. Com'n v. Ronald Adams Cont.Mississippi Supreme Court · 2000
  5. Osprey, Inc. v. Cabana Ltd. PartnershipSupreme Court of South Carolina · 2000

14 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API