Everett v. City of Arkansas City
Supreme Court of Kansas
1Opinion of the Court
The opinion of the court was delivered by
Hopkins, J.:
The action was one to recover interest on a delayed payment for the construction of a sewer. A motion for judgment on the pleadings was sustained, and plaintiff appeals.
The interest in question covers a period from January 23, 1922, the date the sewer was completed and accepted by the city, to October 4, 1922, the date when settlement was made of the principal amount ($116,232).
The defendant city contends it was prevented from making settlement, during a part of the delinquent period, by a mandamus action filed against it in this court by…
2Cases cited1 opinion
- United States Fidelity & Guaranty Co. v. City of PittsburgSupreme Court of Kansas · 1924
3Cited by3 opinions
- United States v. L. R. Foy Construction Co.Court of Appeals for the Tenth Circuit · 1962
- Brown-Crummer Investment Co. v. City of Arkansas CitySupreme Court of Kansas · 1928
- United States v. L. R. Foy Construction CompanyCourt of Appeals for the Tenth Circuit · 1962