United States Fidelity & Guaranty Co. v. Stanley Contracting, Inc.
District Court, D. Oregon
1Opinion of the Court
OPINION AND ORDER
KING, District Judge.
Third-party plaintiff Stanley Contracting, Inc. (“Stanley”) contracted with third-party defendant City of Carlton (“Carlton”) for construction of improvements to Carlton’s water system. When problems arose, Carlton terminated Stanley. Stanley and its principal, Jimmy Stanley, allege claims against Carlton for breach of contract, breach of the implied covenant of good faith, and breach of the warranty of drawings and specifications. Carlton alleged a counterclaim for breach of contract and setoff. Before the court are Third-Party Defendant City of…
2Cases cited16 opinions
- Celotex Corp. v. Catrett, Administratrix of the Estate of CatrettSupreme Court of the United States · 1986
- Yogman v. ParrottOregon Supreme Court · 1997
- Hoffman Construction Co. of Alaska v. Fred S. James & Co.Oregon Supreme Court · 1992
- James L. Ticknor Janet Ticknor Larry Ticknor Tickco Holding, L.L.C. Ticknor Lodging Corporation v. Choice Hotels International, Inc.Court of Appeals for the Ninth Circuit · 2001
- Uptown Heights Associates Ltd. Partnership v. Seafirst Corp.Oregon Supreme Court · 1995
11 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- John T. Jones Construction Co. v. Hoot General ConstructionDistrict Court, S.D. Iowa · 2008
- Big River Construction, Inc. v. City of TillamookCourt of Appeals of Oregon · 2016