1Opinion of the Court
WEINSTEIN, Judge.
Order
On February 6, 1992, the court ordered plaintiff to show cause why its claims based on the contracting officer’s final decision issued April 26, 1990, should not be dismissed for lack of jurisdiction because its complaint here was not filed within twelve months from April 27, 1990, the date plaintiff acknowledges receipt of that decision, as required by § 609(a)(1)1 of the Contract Disputes Act of 1978 (CDA).2
Plaintiff’s response did not dispute that its complaint here was not filed until April 30, 1991, but instead requested, pursuant to Rules of the United States…
2Cases cited23 opinions
- United States v. SherwoodSupreme Court of the United States · 1941
- Browder v. Director, Dept. of Corrections of Ill.Supreme Court of the United States · 1978
- Baldwin County Welcome Center v. BrownSupreme Court of the United States · 1984
- Mohasco Corp. v. SilverSupreme Court of the United States · 1980
- Sibbach v. Wilson & Co.Supreme Court of the United States · 1941
18 more not listed; retrieve them via the Exa API.
3Cited by5 opinions
- Renda Marine, Inc. v. United StatesUnited States Court of Federal Claims · 2006
- NCLN20, Inc. v. United StatesUnited States Court of Federal Claims · 2008
- Liu v. United StatesUnited States Court of Federal Claims · 2010