Quiland, Inc. v. Public Utilities Commission
Supreme Judicial Court of Maine
1Opinion of the CourtGorman, J.
[¶ 1] Quiland, Inc. appeals from an order of the Public Utilities Commission that: (1) upheld Kennebunk, Kennebunk-port & Wells Water District’s individual water metering policy (the Metering Policy) as just and reasonable as applied to property owned by Quiland; and (2) determined that, with certain modifications, the system development charge (SDC) imple mented by the District, and applicable to Quiland, would also be just and reasonable. Quiland argues that the Commission erred when it concluded that the Metering Policy is just and reasonable, asserting that the Commission: (1) ignored…
2Cases cited4 opinions
- Competitive Energy Services LLC v. Public Utilities CommissionSupreme Judicial Court of Maine · 2003
- Bangor Hydro-Electric Co. v. Public Utilities CommissionSupreme Judicial Court of Maine · 1991
- Office of Public Advocate v. Public Utilities CommissionSupreme Judicial Court of Maine · 2005
- Quiland, Inc. v. Public Utilities CommissionSupreme Judicial Court of Maine · 2007
3Cited by1 opinion
- Northern New England Telephone Operations LLC v. Public Utilities CommissionSupreme Judicial Court of Maine · 2013