1Opinion of the CourtSchwellenbach, J.

December 8,1947, Bielas & O’Shaugh-nessy, contractors, entered into a written contract to con*458struct a house in Pullman for Lester R. Brown. They agreed to complete construction on or before March 1, 1948. The agreed price was $10,410.50, to be paid as follows: $1,250 when basement was completed; $1,500 when house roughed in and ready for roofing; $2,500 when heating and plumbing installed; $2,000 when house ready for plastering; $1,500 when ready for painting; $375 when house completed and accepted by owner; balance when garage, sidewalks and yard grading completed.

Bielas & O’Shaughnessy…