In July, 1924, the town of Winthrop made a written contract with a construction company for the *75erection of a high school building. At the same time the construction company, as principal, and the Maryland Casualty Company, as surety, executed and delivered to the town a bond containing this condition: . . if the Principal shall faithfully perform the Contract on his part, and satisfy all claims and demands, incurred for the same, and shall fully indemnify and save harmless the Owner [the town] from all cost and damage which he may suffer by reason of failure so to do, and shall fully…

2Cases cited5 opinions

  1. Norcross v. Board of Appeal of Building DepartmentMassachusetts Supreme Judicial Court · 1926
  2. School Committee of the City of Lowell v. Mayor of LowellMassachusetts Supreme Judicial Court · 1928
  3. Commonwealth v. Commissioner of BanksMassachusetts Supreme Judicial Court · 1922
  4. Central Supply Co. v. United States Fidelity & Guaranty Co.Massachusetts Supreme Judicial Court · 1930
  5. Pike v. Anglo-South American Trust Co.Massachusetts Supreme Judicial Court · 1929

3Cited by10 opinions

  1. Johnson-Foster Co. v. D'Amore Construction Co.Massachusetts Supreme Judicial Court · 1943
  2. Knowlton v. Town of SwampscottMassachusetts Supreme Judicial Court · 1932
  3. Town of Hopkinton v. B. F. Sturtevant Co.Massachusetts Supreme Judicial Court · 1934
  4. Dolben v. Duncan Construction Co.Massachusetts Supreme Judicial Court · 1931
  5. Waite Hardware Co. v. Ardini & Pfau, Inc.Massachusetts Supreme Judicial Court · 1959

5 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API