Legal Opinion

Centaur Construction Co. v. United States

United States Court of Claims

Decided January 6, 1947No. 46242PublishedCited by 2 opinions

1Opinion of the CourtJones, Judge

This is a suit for remission of liquidated damages and additional costs incurred due to change orders in connection with a construction contract.

The contract, dated November 20,1939, called for construction work at the New York Navy Yard.

After the work was started December 26,1939, plaintiff was directed by the officers in charge to drive certain test piles. These tests disclosed conditions materially different from those shown on the drawings and the specifications.

Revised plans were drawn, and plaintiff estimated that the additional cost would be $87,450 and estimated the additional time…

2Cases cited2 opinions

  1. Rollins v. United StatesUnited States Court of Claims · 1888
  2. W. S. King & Co. v. United StatesUnited States Court of Claims · 1934

3Cited by2 opinions

  1. BOLINDERS COMPANY v. United StatesUnited States Court of Claims · 1957
  2. Viking Construction Corp. v. United StatesUnited States Court of Claims · 1954

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API