Dravo Corp. v. United States
United States Court of Claims
1Opinion of the CourtNichols, Judge
This case is before the court on plaintiff’s motion for summary judgment and defendant’s cross motion for summary judgment.
Plaintiff entered into a fixed price contract (No. DACW01-68-C-0088) with the Department of the Army on April IT, 1968, for the construction of the Jones Bluff Lock and Dam on the Alabama Elver in Alabama. Article 50 of the general provisions of the contract entitled “Value Engineering Incentive” provided that the contractor and the Government would share in savings in the cost of performance of the contract which resulted from changes proposed by the contractor. On May…
2Cases cited8 opinions
- United States v. Bethlehem Steel Corp.Supreme Court of the United States · 1942
- The Firestone Tire & Rubber Company v. The United StatesUnited States Court of Claims · 1971
- Chris Berg, Inc. v. The United StatesUnited States Court of Claims · 1970
- Morrison-Knudsen Company, Inc. v. The United StatesUnited States Court of Claims · 1968
- General Builders Supply Co., Inc., on Behalf of Itself and for the Benefit of Hupp, Inc. v. The United StatesUnited States Court of Claims · 1969
3 more not listed; retrieve them via the Exa API.
3Cited by14 opinions
- Pacific Architects & Engineers Inc. v. United StatesUnited States Court of Claims · 1974
- State v. CosgroveSupreme Court of Connecticut · 1982
- American Electric Contracting Corp. v. United StatesUnited States Court of Claims · 1978
- Grismac Corp. v. United StatesUnited States Court of Claims · 1977
- Fairfield Scientific Corp. v. United StatesUnited States Court of Claims · 1979
9 more not listed; retrieve them via the Exa API.