Bickett Coal & Coke Co. v. United States

United States Court of Claims

Decided February 4, 1929No. D-1PublishedCited by 2 opinions

1Opinion of the CourtGraham, Judge

This claim grows out of a contract of date July 1, 1920, for 67,200 tons of bituminous coal run-of-mine, at $4.50 per ton, unit price. The contract provided that—

“The contractor shall furnish and deliver to the United States, and the United States shall accept and pay for, the articles of work described, and upon the terms and conditions set forth in ‘Schedule A’ attached hereto and by reference made a part hereof.”

Schedule A provided, inter alia, that the coal was to be delivered f. o. b. mines, Riley, Vigo County, Indiana, and the schedule of delivery was as follows:

“As called for on or…

2Cases cited8 opinions

  1. Knox v. LeeSupreme Court of the United States · 1871
  2. Horowitz v. United StatesSupreme Court of the United States · 1925
  3. Jones v. United StatesUnited States Court of Claims · 1865
  4. United States v. Burton Coal Co.Supreme Court of the United States · 1927
  5. Wilson v. United StatesSupreme Court of the United States · 1875

3 more not listed; retrieve them via the Exa API.

3Cited by2 opinions

  1. Shader Contractors, Inc. And Citizens National Bank of Orlando, Assignee v. United StatesUnited States Court of Claims · 1960
  2. Gemsco, Inc. v. United StatesUnited States Court of Claims · 1950

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API