Legal Opinion

White Buffalo Construction, Inc. v. United States

United States Court of Federal Claims

Decided February 22, 2002No. 98-767CPublishedCited by 13 opinions

1Opinion of the Court

OPINION

FUTEY, Judge.

This contract case is before the court following a trial on damages. Plaintiff asserts a claim for approximately $1,662,5911 for costs related to its contract with defendant that was originally terminated for default. The parties later agreed to convert the default into a termination for convenience. Plaintiff alleges it is entitled to compensation for numerous costs related to its work on this contract. Defendant challenges most of plaintiffs claims asserting that the proposed costs are either unallowable or unsubstantiated. Defendant believes the court should only award…

2Cases cited20 opinions

  1. United States v. KingSupreme Court of the United States · 1969
  2. Renegotiation Board v. Bannercraft Clothing Co.Supreme Court of the United States · 1974
  3. Gerald Alan Brown, and Charles v. Darnell v. United StatesCourt of Appeals for the Federal Circuit · 1997
  4. Bluebonnet Savings Bank, F.S.B., Stone Capital, Inc. (Formerly Known as Cfsb Corporation), and James M. Fail v. United StatesCourt of Appeals for the Federal Circuit · 2001
  5. Lisbon Contractors, Inc. v. The United StatesCourt of Appeals for the Federal Circuit · 1987

15 more not listed; retrieve them via the Exa API.

3Cited by13 opinions

  1. Bluebonnet Savings Bank FSB v. United StatesUnited States Court of Federal Claims · 2005
  2. Praecomm, Inc. v. United StatesUnited States Court of Federal Claims · 2007
  3. Dart Advantage Warehousing, Inc. v. United StatesUnited States Court of Federal Claims · 2002
  4. Dwen v. United StatesUnited States Court of Federal Claims · 2004
  5. NCLN20, Inc. v. United StatesUnited States Court of Federal Claims · 2011

8 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API