R.P. Wallace, Inc. v. United States
United States Court of Federal Claims
1Opinion of the Court
OPINION
ALLEGRA, Judge.
At least since the shock of exploding fireworks caused the scales to fall on poor Helen Palsgraf, courts have applied temporal and spatial limitations on the availability of tort damages, invoking familiar doctrines such as proximate cause and foreseeability. See Palsgraf v. Long Island R. Co., 248 N.Y. 339, 162 N.E. 99 (1928). Similar principia have evolved in contract cases and, not surprisingly, have wended them way into the regulatory and decisional fabric of Federal procurement law, particularly in assessing responsibility for delays in the completion of a contract,…
2Cases cited43 opinions
- Palsgraf v. Long Island R.R. Co.New York Court of Appeals · 1928
- United States v. SpearinSupreme Court of the United States · 1918
- Newell Companies, Inc. v. Kenney Manufacturing Company, Defendant/cross-AppellantCourt of Appeals for the Federal Circuit · 1989
- J. D. Hedin Construction Company, Inc., for Its Own Use and for the Use of Fischbach & Moore, Its Sub-Contractor v. The United StatesUnited States Court of Claims · 1965
- Melvin Wilner, D/B/A Wilner Construction Company v. United StatesCourt of Appeals for the Federal Circuit · 1994
38 more not listed; retrieve them via the Exa API.
3Cited by14 opinions
- George Sollitt Construction Co. v. United StatesUnited States Court of Federal Claims · 2005
- United States ex rel. Chasney & Co. v. Hartford Accident & Indemnity Co.District Court, D. Maryland · 2016
- ADP Marshall, Inc. v. NORESCO, LLCDistrict Court, D. Rhode Island · 2010
- Sunshine Construction & Engineering, Inc. v. United StatesUnited States Court of Federal Claims · 2005
- United Medical Supply Co. v. United StatesUnited States Court of Federal Claims · 2005
9 more not listed; retrieve them via the Exa API.