Harvey Radio Laboratories, Inc. v. United States
United States Court of Claims
1Opinion of the CourtLittletoN, Judge
This is an action on a contract to recover the balance of the price stated in the contract, alleged to be due and unpaid. In April 1946, plaintiff and defendant entered into a letter contract whereby plaintiff agreed to develop and fabricate for defendant certain radar equipment for use in long range navigation. In February 1947, a definitive fixed-price contract superseding the letter contract was executed, providing for a total contract price of $1,146,780.54. The contract specified that the prices contained therein were subject to revision in accordance with the provisions of Article 40…
2Cases cited4 opinions
- Bergeron v. MansourCourt of Appeals for the First Circuit · 1945
- Robinson v. Commissioner of Internal RevenueCourt of Appeals for the Sixth Circuit · 1939
- Simmons v. Burlington, Cedar Rapids & Northern Railway Co.Supreme Court of the United States · 1895
- First Federal Trust Co. v. First Nat. BankCourt of Appeals for the Ninth Circuit · 1924
3Cited by20 opinions
- Miller Elevator Co. v. United StatesUnited States Court of Federal Claims · 1994
- Acme Process Equipment Co. v. United StatesUnited States Court of Claims · 1965
- Hoffman Motors Corporation v. Alfa Romeo SpADistrict Court, S.D. New York · 1965
- Penn-Ohio Steel Corporation v. The United StatesUnited States Court of Claims · 1965
- Copco Steel & Engineering Co. v. The United StatesUnited States Court of Claims · 1965
15 more not listed; retrieve them via the Exa API.