Hulet v. Idaho Public Utilities Commission
Idaho Supreme Court
1Opinion of the Court
WALTERS,' Justice.
This is an appeal from a final order of the Idaho Public Utilities Commission (IPUC) dismissing Jay Hulet’s complaint requesting that Idaho Power Co. retroactively accept his farm into the Company’s Irrigation BuyBack Program for the 2001 growing season. We affirm the dismissal.
FACTS AND PROCEDURE
Hulet, an irrigator with farms at Oreana and Murphy Flats, Idaho, received a Request for Proposals (RFP), an Offer Form, a bid form, and a cover letter from Idaho Power regarding its Irrigation Buy-Back Program. The RFP, which detailed the program requirements, specifically stated…
2Cases cited4 opinions
- Utah Power & Light Co. v. Idaho Public Utilities CommissionIdaho Supreme Court · 1981
- Rosebud Enterprises, Inc. v. Idaho Public Utilities CommissionIdaho Supreme Court · 1996
- Iindustrial Customers of Idaho Power v. Idaho Public Utilities CommissionIdaho Supreme Court · 2000
- Building Contractors Ass'n of Southwestern Idaho, Inc. v. Idaho Public Utilities CommissionIdaho Supreme Court · 1996
3Cited by2 opinions
- In Re Jay Hulet's Complaint Regarding Idaho Power Company's Irr. Buy-Back ProgramIdaho Supreme Court · 2003
- Idaho Power Co. v. Idaho Public Utilities CommissionIdaho Supreme Court · 2004