Lano v. Osberg Construction Co.
Washington Supreme Court
1Opinion of the CourtHunter, J.
— This is an action for damages for wrongful termination of a subcontract to clear and grub a state highway right-of-way in Pacific County.
In November, 1958, defendant (respondent) Osberg Construction Company, as prime contractor, executed a contract with the state of Washington to construct a portion of the Tokeland-Raymond highway.
Plaintiffs (appellants) executed a subcontract with defendant covering the clearing and grubbing portion of the prime contract. The plaintiffs, who were primarily loggers, contracted with a third party to perform the clearing and grubbing after the removal of the…
2Cases cited2 opinions
- Kane v. KlosWashington Supreme Court · 1957
- Vance v. Mutual Gold Corp.Washington Supreme Court · 1940
3Cited by9 opinions
- Dravo Corp. v. L. W. Moses Co.Court of Appeals of Washington · 1971
- Cascade Auto Glass v. PROGRESSIVE CAS. INS.Court of Appeals of Washington · 2006
- Cascade Auto Glass, Inc. v. Progressive Casualty InsuranceCourt of Appeals of Washington · 2006
- Associated Petroleum Products, Inc. v. Northwest Cascade, Inc.Court of Appeals of Washington · 2009
- Sak & Associates, / Cross- Res. v. Ferguson Construction, / Cross-app.Court of Appeals of Washington · 2015
4 more not listed; retrieve them via the Exa API.