Notwithstanding the case has been tried and submitted on the facts, the defendant has filed a motion to dismiss the petition on the ground that it is based upon an alleged breach of the contract occurring more than six years prior to the time when the action was commenced.

While the petition does allege that in several respects the defendant failed to comply with the contract and that these specific failures occurred more than six years prior to the time when the suit was commenced, less than six years elapsed between the time when the contract was completed and this suit was begun.. If the…

Also in this document: Opinion of the Court · Green.

2Cases cited3 opinions

  1. Pink v. United StatesUnited States Court of Claims · 1937
  2. Myerle v. United StatesUnited States Court of Claims · 1896
  3. Schuler & McDonald, Inc. v. United StatesUnited States Court of Claims · 1937

3Cited by12 opinions

  1. Nager Electric Company, Inc. And Keystone Engineering Corporation v. The United StatesUnited States Court of Claims · 1966
  2. Dale Construction Co. v. United States, Seaboard Surety Co.United States Court of Claims · 1964
  3. Northern Helex Co. v. United StatesUnited States Court of Claims · 1972
  4. Anthony P. Miller, Inc. v. The United StatesUnited States Court of Claims · 1965
  5. Holton v. United StatesUnited States Court of Claims · 1946

7 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API