Albany Engineering Corp. v. Federal Energy Regulatory Commission
Court of Appeals for the D.C. Circuit
1Opinion of the Court
Opinion for the Court filed by Senior Circuit Judge WILLIAMS.
Concurring opinion filed by Circuit Judge BROWN.
WILLIAMS, Senior Circuit Judge:
An upstream dam typically will render the downstream flow more even and predictable, enabling downstream hydropower plants to operate at a higher capacity. Farmington River Power Co. v. FERC, 103 F.3d 1002, 1004 (D.C.Cir.1997); see also 18 C.F.R. § 11.10(a)(2). To enable the upstream firms to recoup part of the cost of conferring these “headwater benefits,” Congress in § 10(f) of the Federal Power Act (“FPA”), 16 U.S.C. § 803(f) (2006), directed the…
2Cases cited22 opinions
- Chevron U. S. A. Inc. v. Natural Resources Defense Council, Inc.Supreme Court of the United States · 1984
- Securities & Exchange Commission v. Chenery Corp.Supreme Court of the United States · 1943
- Medtronic, Inc. v. LohrSupreme Court of the United States · 1996
- Watters v. Wachovia Bank, N. A.Supreme Court of the United States · 2007
- Fidelity Federal Savings & Loan Ass'n v. De La CuestaSupreme Court of the United States · 1982
17 more not listed; retrieve them via the Exa API.
3Cited by27 opinions
- Niagara Mohawk Power Corp. v. Hudson River-Black River Regulating DistrictCourt of Appeals for the Second Circuit · 2012
- Fayus Enterprises v. BNSF Railway Co.Court of Appeals for the D.C. Circuit · 2010
- Lindeen v. Securities & Exchange CommissionCourt of Appeals for the D.C. Circuit · 2016
- Erie Boulevard Hydropower, LP v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 2017
- Akins v. Federal Election CommissionDistrict Court, District of Columbia · 2010
22 more not listed; retrieve them via the Exa API.