In Re Declaratory Ruling of Northwestern Public Service Co.
South Dakota Supreme Court
1Opinion of the Court
TIMM, Circuit Judge.
[¶ 1] On January 3, 1995, the Public Utilities Commission (PUC) authorized Northwestern Public Service Company (NWPS) to replace Northern Electric Cooperative (NEC) as supplier of electricity to Hub City, Inc. NEC appealed to the circuit court, Fifth Judicial Circuit. There, the PUC’s decision was overturned. The PUC and NWPS appeal to this Court. Here, the circuit court is affirmed.
BACKGROUND
[¶ 2] In 1977 Safeguard Automotive Corporation (Safeguard) operated a manufacturing plant in the Aberdeen Industrial Park. The plant was located in the assigned service area of NWPS.…
2Cases cited13 opinions
- Permann v. South Dakota Department of Labor, Unemployment Insurance DivisionSouth Dakota Supreme Court · 1987
- Simpson v. TobinSouth Dakota Supreme Court · 1985
- Whalen v. WhalenSouth Dakota Supreme Court · 1992
- Egemo v. FloresSouth Dakota Supreme Court · 1991
- In Re the Appeal of the Sales Tax Refund Applications of Black Hills Power & Light Co.South Dakota Supreme Court · 1980
8 more not listed; retrieve them via the Exa API.
3Cited by10 opinions
- Steinberg v. South Dakota Department of Military & Veterans AffairsSouth Dakota Supreme Court · 2000
- In Re West River Elec. Ass'n, Inc.South Dakota Supreme Court · 2004
- Dale v. YoungSouth Dakota Supreme Court · 2015
- Capital Motors, LLC v. SchiedSouth Dakota Supreme Court · 2003
- Establishment of Switched Access Rates for U.S. v. AT & T Communications of Midwest Inc.South Dakota Supreme Court · 2000
5 more not listed; retrieve them via the Exa API.