In Re the Arbitration Between HRH Construction Corp. & Bethlehem Steel Corp.
New York Court of Appeals
1Opinion of the Court
OPINION OF THE COURT
Jones, J.
We hold that a provision in an otherwise broad arbitration clause that the determination of particular disputes in another judicial or arbitration proceeding shall be determinative and conclusive between the parties, does not limit the scope of arbitration but constitutes a directive as to how the dispute in question shall be resolved in arbitration.
Petitioner in this proceeding for a stay of arbitration is the general contractor in the construction of the Citicorp Center, a commercial complex on Lexington Avenue in the City of New York, under a contract with the…
2Cases cited4 opinions
- Matter of Am. Ins. Co (Messinger)New York Court of Appeals · 1977
- In re Arbitration between Exercycle Corp. & MarattaNew York Court of Appeals · 1961
- Pearl Street Development Corp. v. Conduit & Foundation Corp.New York Court of Appeals · 1976
- Walter A. Stanley & Son, Inc. v. Trustees of Hackley SchoolNew York Court of Appeals · 1977
3Cited by7 opinions
- Miller v. RunyonCourt of Appeals for the Seventh Circuit · 1996
- Levine v. Advest, Inc.Supreme Court of Connecticut · 1998
- Collins v. D.R. Horton, Inc.District Court, D. Arizona · 2003
- F.N. Wolf & Co. v. BrothersNew York Supreme Court · 1994
- In re the Arbitration between Todd Shipyards Corp. & Marine Vessel Leasing Corp.Appellate Division of the Supreme Court of the State of New York · 1979
2 more not listed; retrieve them via the Exa API.