Gordon v. Robinson Homes, Inc.
Massachusetts Supreme Judicial Court
1Opinion of the CourtSpalding, J.
This is an action of contract on a bond executed by the defendant Bobinson Homes, Inc. (Bobin-son), as principal and the defendant American Surety Company (American) as surety. From an order sustaining the defendants’ demurrer the plaintiff appealed.
The averments of the declaration in substance are • as follows: On April 25, 1956, Bobinson as principal and American as surety executed and delivered to the city of Beverly a bond in the penal sum of $35,000 “conditioned upon the performance by . . . [Bobinson] of an agreement with the city ... to make certain improvements to land ... in…
2Cases cited6 opinions
- Johnson-Foster Co. v. D'Amore Construction Co.Massachusetts Supreme Judicial Court · 1943
- Town of Stoneham v. SaveloMassachusetts Supreme Judicial Court · 1960
- Philip Carey Manufacturing Co. v. Peerless Casualty Co.Massachusetts Supreme Judicial Court · 1953
- Waite Hardware Co. v. Ardini & Pfau, Inc.Massachusetts Supreme Judicial Court · 1959
- Robinson Clay Product Co. v. Beacon Construction Co. of Massachusetts, Inc.Massachusetts Supreme Judicial Court · 1959
1 more not listed; retrieve them via the Exa API.
3Cited by10 opinions
- Castle Estates v. Park & Planning Board of MedfieldMassachusetts Supreme Judicial Court · 1962
- COSTANZA & BERTOLINO v. Planning Bd. of North ReadingMassachusetts Supreme Judicial Court · 1971
- Lyman v. Planning Board of WinchesterMassachusetts Supreme Judicial Court · 1967
- Stoner v. Planning Board of AgawamMassachusetts Supreme Judicial Court · 1971
- Wheatley v. Planning Board of HinghamMassachusetts Appeals Court · 1979
5 more not listed; retrieve them via the Exa API.