Legal Opinion

James McHugh Sons, Inc. v. United States

United States Court of Claims

Decided May 3, 1943No. 43154PublishedCited by 11 opinions

1Opinion of the CourtWhitaker, Judge

On December 1,1933, plaintiff entered into a contract with the defendant for the construction of 18 four-family apartments at Fort Sill, Oklahoma. It sues to recover on five items of work it was required to do which it alleges were not called for by the contract. Its first claim is for additional back-filling in the amount of $195.24; the second, for additional cost of constructing fireplaces $393.00; third, for the cost of placing mortar between tiles, $4,298.13; fourth, for the cost of louvers, $40.52; and fifth, for the cost of grinding and rubbing concrete surfaces, $3,174.15.

To all of…

2Cited by11 opinions

  1. WRB Corp. v. United StatesUnited States Court of Claims · 1968
  2. Stein Bros. Mfg. Co. v. United StatesUnited States Court of Claims · 1963
  3. New York Shipbuilding Corporation v. The United StatesUnited States Court of Claims · 1967
  4. C. J. Langenfelder & Son, Inc. v. United StatesUnited States Court of Claims · 1965
  5. Jefferson Construction Co. v. United StatesUnited States Court of Claims · 1960

6 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API