Legal Opinion

Clearwater Constructors, Inc. v. United States

United States Court of Federal Claims

Decided April 28, 2006No. 01-351CPublishedCited by 2 opinions

1Opinion of the Court

OPINION and ORDER

MEROW, Senior Judge.

INTRODUCTION

This contract dispute action is before the court upon defendant’s motion for summary judgment and plaintiffs cross-motion for summary judgment, both brought pursuant to Rule 56(b) of the Rules of the United States Court of Federal Claims (“RCFC”).

BACKGROUND

Facts and Procedural History

On February 20, 1986, Clearwater Constructors, Inc. (“Clearwater”) and the United States Army Corps of Engineers (“the Corps”) entered into Contract No. DACA45-86-C-0068 (“contract”) in the amount of $17,487,000 for the construction of a “Three Bay Hangar” for B-1B…

2Cases cited24 opinions

  1. Anderson v. Liberty Lobby, Inc.Supreme Court of the United States · 1986
  2. Celotex Corp. v. Catrett, Administratrix of the Estate of CatrettSupreme Court of the United States · 1986
  3. United States v. SpearinSupreme Court of the United States · 1918
  4. Sweats Fashions, Inc. v. Pannill Knitting Company, Inc.Court of Appeals for the Federal Circuit · 1987
  5. Avia Group International, Inc., (Formerly Pensa, Inc.) v. L.A. Gear California, Inc.Court of Appeals for the Federal Circuit · 1988

19 more not listed; retrieve them via the Exa API.

3Cited by2 opinions

  1. Metric Construction Co. v. United StatesUnited States Court of Federal Claims · 2006
  2. Metric Construction Co. v. United StatesUnited States Court of Federal Claims · 2008

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API