Metric Construction Company, Inc. (Metric) seeks $2,100,340, plus interest, court costs and attorneys fees, for costs it incurred during the construction of a building for the United States Army Corps of Engineers (Corps).2

*180BACKGROUND

In 1999, Metric was awarded Contract No. DACA05-99-C-0030 (contract) to construct the Deployable Medical Systems Warehouse (warehouse) at Hill Air Force Base in Utah. Compl. at 2. When the warehouse roof developed serious leaks, the Corps required Metric to install a new roof. Metric’s claims before this court stem largely from the costs Metric…

2Cases cited34 opinions

  1. United States v. SpearinSupreme Court of the United States · 1918
  2. Nvt Technologies, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2004
  3. Dawco Construction, Inc. v. The United StatesCourt of Appeals for the Federal Circuit · 1991
  4. Helene Curtis Industries, Inc. v. The United StatesUnited States Court of Claims · 1963
  5. Mega Construction Co. v. United StatesUnited States Court of Federal Claims · 1993

29 more not listed; retrieve them via the Exa API.

3Cited by3 opinions

  1. Penzel Constr. Co. v. Jackson R-2 Sch. Dist., Warner-Nease-Bost Architects & Henthorn, Sandmeyer & Co.Missouri Court of Appeals · 2017
  2. Information Systems & Networks, Corp. v. United StatesUnited States Court of Federal Claims · 2008
  3. Metric Construction Co. v. United StatesUnited States Court of Federal Claims · 2008

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API