Moseman Construction Co. v. Shappert Engineering Co.
District Court, C.D. Illinois
1Opinion of the Court
OPINION
RICHARD MILLS, District Judge:
First, can only the public body on which a public mechanic’s lien has been served complain about the sufficiency of the lien?
No.
Second, does a lien for “materials and labor furnished” comply with a requirement that liens state with particularity the items and amounts that are due?
Yes.
This cause is before the Court on Defendant-contractor’s motion to dismiss Plaintiff-subcontractor’s complaint for an accounting for its failure to follow the statutory requirements set forth in Ill.Rev.Stat. ch. 82, ¶ 23 (1989).
Denied.
I. Facts
In March, 1986, Defendant and the…
2Cases cited15 opinions
- Conley v. GibsonSupreme Court of the United States · 1957
- Car Carriers, Inc. v. Ford Motor Company and Nu-Car Carriers, Inc.Court of Appeals for the Seventh Circuit · 1984
- Greer v. Illinois Housing Development AuthorityIllinois Supreme Court · 1988
- Jorge Gomez v. Illinois State Board of Education and Ted Sanders, in His Official Capacity as Illinois State Superintendent of EducationCourt of Appeals for the Seventh Circuit · 1987
- Stanley Green, as Assignee of Dexter Hopkins, Cross v. The J.C. Penney Auto Insurance Company, Inc., a Corporation, Defendant- Cross-AppellantCourt of Appeals for the Seventh Circuit · 1986
10 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Walker Process Equipment v. Advance Mechanical System, Inc.Appellate Court of Illinois · 1996
- Walker Process Equipment v. Advance Mechanical System, Inc.Appellate Court of Illinois · 1996