Office of Public Utility Counsel v. Public Utility Commission
Texas Supreme Court
1Opinion of the CourtJustice Enoch
in which Chief Justice PHILLIPS, Justices HIGHTOWER, HECHT and CORNYN join. Justice GAMMAGE not sitting.
This is an administrative appeal from a final order of the Texas Public Utility Commission (Commission) which granted West Texas Utilities’ (WTU) request for deferred accounting treatment for certain costs related to a new generating plant, Oklaunion Power Station Unit No. 1 (Oklaunion).1 The question presented by this case is whether the Commission has the authority under the Public Utility Regulatory Act (PURA)2 to allow a public utility to defer certain costs incurred during the…
2Cases cited10 opinions
- Federal Power Commission v. Hope Natural Gas Co.Supreme Court of the United States · 1944
- Bluefield Water Works & Improvement Co. v. Public Service CommissionSupreme Court of the United States · 1923
- State v. Public Utility Com'n of TexasTexas Supreme Court · 1994
- Suburban Utility Corp. v. Public Utility CommissionTexas Supreme Court · 1983
- Railroad Com'n of Texas v. Lone Star Gas Co.Texas Supreme Court · 1983
5 more not listed; retrieve them via the Exa API.
3Cited by9 opinions
- Public Utility Commission v. GTE-Southwest, Inc.Texas Supreme Court · 1995
- West Texas Utilities Co. v. Office of Public Utility CounselCourt of Appeals of Texas · 1995
- State of Texas' Agencies & Institutions of Higher Learning v. Public Utility CommissionCourt of Appeals of Texas · 2014
- Pub. Util. Com'n v. Gte-SouthwestTexas Supreme Court · 1995
- Office of Public Utility Counsel v. Public Utility CommissionTexas Supreme Court · 1994
4 more not listed; retrieve them via the Exa API.