Lacchi Construction Co. v. United States
United States Court of Claims
1Opinion of the CourtLittletoN, Judge
Plaintiff seeks to recover $29,256.22 under nine separate items of a claim made under a contract with defendant entered into July 15, 1933, to furnish all labor and materials and perform all work required for the construction of a Booster Pumping Plant to serve as a dam across the Dale-carlia Eeservoir serving the District of Columbia. The several items of the claim now urged, and with respect to *353which findings of fact established by the greater weight of the evidence of record have been made, are as follows:
Claim 1. Repair cofferdam_$6,068. 72
Profit_ 606.87
Claim 2. Rental cofferdam for extra…
2Cases cited1 opinion
- Seeds v. United StatesUnited States Court of Claims · 1940
3Cited by4 opinions
- Acme Process Equipment Co. v. United StatesUnited States Court of Claims · 1965
- Acme Process Equipment Co. v. United StatesCourt of Appeals for the First Circuit · 1965
- National Trailer Convoy, Inc. v. The United StatesUnited States Court of Claims · 1965
- Remington Rand Inc. v. United StatesUnited States Court of Claims · 1954