Legal Opinion

Borden, Inc. v. Federal Energy Regulatory Commission

Court of Appeals for the Fifth Circuit

Decided October 21, 1988No. 87-4710PublishedCited by 9 opinions

1Opinion of the Court

JOHNSON, Circuit Judge:

Petitioners Borden, Inc.; Basic Incorporated; Gardinier, Inc.; and Florida Gas Transmission Company seek judicial review of an order 1 of the Federal Energy Regulatory Commission directing Borden, Basic, and Gardinier to make so-called monetary payback with interest. We affirm.

I. Facts and Procedural History

As explained in a previous opinion in this case:

Florida Gas Transmission Company operates a gas transmission line from Texas to Central and Northern Florida. In 1959, the gas company filed a curtailment plan with the Commission due to expected shortages in the supply…

2Cases cited51 opinions

  1. Permian Basin Area Rate CasesSupreme Court of the United States · 1968
  2. Orr v. OrrSupreme Court of the United States · 1979
  3. Federal Power Commission v. Natural Gas Pipeline Co.Supreme Court of the United States · 1942
  4. Federal Power Commission v. Louisiana Power & Light Co.Supreme Court of the United States · 1972
  5. Mobil Oil Corp. v. Federal Power CommissionSupreme Court of the United States · 1974

46 more not listed; retrieve them via the Exa API.

3Cited by9 opinions

  1. Torrington Co. v. United StatesUnited States Court of International Trade · 1990
  2. In Re Linerboard Antitrust LitigationDistrict Court, E.D. Pennsylvania · 2007
  3. Gulf States Utilities Co. v. Federal Energy Regulatory CommissionCourt of Appeals for the Fifth Circuit · 1993
  4. El Paso Electric Co. v. Federal Energy Regulatory CommissionCourt of Appeals for the Fifth Circuit · 2000
  5. Procter & Gamble Co. v. Stone Container Corp.District Court, E.D. Pennsylvania · 2007

4 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API