Carroll v. United States
United States Court of Claims
1Opinion of the CourtGRAham, Judge
The plaintiffs seek to recover the cost of additional labor incurred and additional superintendence in the performance of work under a written contract due to delays arising by reason of changes in the plans and specifications where the terms of the contract provide for such changes and also provide for extensions of time to the contractor for delays caused by the Government with the statement “ that delays caused by the act of the Government will be regarded as unavoidable delays.”
The formal written contract between the parties provided for the determination of any additional cost due to…
2Cases cited2 opinions
- H. E. Crook Co. v. United StatesSupreme Court of the United States · 1926
- Lange v. United StatesUnited States Court of Claims · 1926
3Cited by1 opinion
- Levering & Garrigues Co. v. United StatesUnited States Court of Claims · 1931