Snyder-Lynch Motors, Inc. v. United States
United States Court of Claims
1Opinion of the Court
LARAMORE, Judge.
This is an action for damages arising out of two contracts. Under a facilities contract, Ord-244, the Government agreed to furnish plaintiff certain facilities needed to perform a supply contract. The second contract, DA-04-495-ORD-242, in the amount of $1,054,207.50, was for the rebuilding of 750 tank engines.
Plaintiff claims for recovery in four counts against the United States, the sum of $782,167.23 for alleged misrepresentation and breach of the two contracts above referred to. Under count one, claim is made for $101,739.16 of additional costs for extra work in the…
2Cases cited3 opinions
- Ragonese & Scaravelli v. United StatesUnited States Court of Claims · 1954
- Ragonese v. United StatesUnited States Court of Claims · 1954
- Bateson-Stolte, Inc. v. United StatesUnited States Court of Claims · 1959
3Cited by17 opinions
- Helene Curtis Industries, Inc. v. The United StatesUnited States Court of Claims · 1963
- WRB Corp. v. United StatesUnited States Court of Claims · 1968
- James A. Boyajian, Assignee of Triumph Manufacturing Company, Bankrupt v. The United StatesUnited States Court of Claims · 1970
- Travis T. Womack, Jr. And John R. Vorhies, Formerly Partners of Petroleum Ownership Map Company (A Dissolved Partnership) v. The United StatesUnited States Court of Claims · 1968
- Helene Curtis Industries, Inc. v. United StatesUnited States Court of Claims · 1963
12 more not listed; retrieve them via the Exa API.