United States Fidelity & Guaranty Co. v. Bangor Area Joint School Authority
District Court, E.D. Pennsylvania
1Opinion of the Court
MEMORANDUM AND ORDER
TROUTMAN, District Judge.
On January 29, 1968, Fraim Construction Company entered into a contract with defendant school authority for the construction of a new junior high school in Bangor, Pennsylvania, for the sum of $2,058,839.68. On or about the same date, plaintiff [U.S.F.&G.], as surety, and Fraim, as principal, executed and delivered performance and labor and material payment bonds in connection with the construction project with defendant school authority as obligee. In February 1971, Fraim defaulted and purportedly assigned all his rights under the con struction…
2Cases cited12 opinions
- Erie Railroad v. TompkinsSupreme Court of the United States · 1938
- Landis v. North American Co.Supreme Court of the United States · 1936
- United Steelworkers v. Warrior & Gulf Navigation Co.Supreme Court of the United States · 1960
- Hanna v. PlumerSupreme Court of the United States · 1965
- Merritt-Chapman & Scott Corporation v. Pennsylvania Turnpike CommissionCourt of Appeals for the Third Circuit · 1967
7 more not listed; retrieve them via the Exa API.
3Cited by8 opinions
- Litton RCS, Inc. v. Pennsylvania Turnpike CommissionDistrict Court, E.D. Pennsylvania · 1974
- Ice City, Inc. v. Insurance Co. of North AmericaSupreme Court of Pennsylvania · 1974
- Vespe Contracting Co. v. Anvan CorporationDistrict Court, E.D. Pennsylvania · 1975
- Cecala v. MooreDistrict Court, N.D. Illinois · 1997
- Anderson v. Delta Funding Corp.District Court, N.D. Ohio · 2004
3 more not listed; retrieve them via the Exa API.