Mustang Run Wind Project, LLC v. Osage County Board of Adjustment
Supreme Court of Oklahoma
1Opinion of the CourtEdmondson, J.
¶ 1 Mustang Run Wind Project, LLC, (Mustang) filed an application with the Osage County Board of Adjustment for a conditional use permit involving between 9,406 and 9,453 acres of land. Mustang proposed to use the land for placing sixty-eight wind turbines on less than 150 acres and generating electricity. 1 Public meetings on the proposed wind energy facility were held in April and May 2014. The proposed facility is close to another “wind farm” which had obtained a permit three years previously. Mustang’s application included land zoned for agricultural use and was then being used for…
2Cases cited42 opinions
- Village of Euclid v. Ambler Realty Co.Supreme Court of the United States · 1926
- Lingle v. Chevron U. S. A. Inc.Supreme Court of the United States · 2005
- Village of Belle Terre v. BoraasSupreme Court of the United States · 1974
- Koontz v. St. Johns River Water Management Dist.Supreme Court of the United States · 2013
- City of Edmonds v. Oxford House, Inc.Supreme Court of the United States · 1995
37 more not listed; retrieve them via the Exa API.
3Cited by23 opinions
- OSAGE NATION v. BD. OF COMMISSIONERS OF OSAGE COUNTY and OSAGE NATION v. OSAGE COUNTY BD. OF ADJUSTMENTSupreme Court of Oklahoma · 2017
- BOYLE v. ASAP ENERGY, INC.Supreme Court of Oklahoma · 2017
- Compsource Mut. Ins. Co. v. Oklahoma Tax CommissionSupreme Court of Oklahoma · 2018
- HENSLEY v. STATE FARM FIRE AND CASUALTY CO.Supreme Court of Oklahoma · 2017
- COMPSOURCE MUTUAL INSUR. CO. v. STATE ex rel. OKLA. TAX COMM. and OKLA. ASSOC. OF ELECTRIC SELF INSURERS FUND v. STATE OF OKLA. TAX COMM.Supreme Court of Oklahoma · 2018
18 more not listed; retrieve them via the Exa API.