Wiggins Construction Co. v. Joint School District No. 3
Wisconsin Supreme Court
1Opinion of the CourtHanley, J.
There are two issues presented by this appeal: (1) Did the trial court err in finding the work as constructed by respondent defective as a matter of law, despite the jury verdict to the contrary; and (2) did the trial court in this case properly apply the Powers rule in assessing damages against respondent in the sum of $1,800?
The building contract requiring the roof deck to be constructed with a four-inch pitch to the east and to the west was of importance since it was to be used as a classroom and as a means of ingress and egress to the adjoining school building. Proper drainage was…
2Cases cited7 opinions
- Powers v. Allstate InsuranceWisconsin Supreme Court · 1960
- Ashland Lime, Salt & Cement Co. v. ShoresWisconsin Supreme Court · 1899
- Lambrecht v. State Highway CommissionWisconsin Supreme Court · 1967
- Dudley v. BeckWisconsin Supreme Court · 1854
- Hennington v. ValuchWisconsin Supreme Court · 1965
2 more not listed; retrieve them via the Exa API.
3Cited by10 opinions
- S & M Rotogravure Service, Inc. v. BaerWisconsin Supreme Court · 1977
- Lien v. McGladrey & PullenSouth Dakota Supreme Court · 1993
- Goebel v. National Exchangors, Inc.Wisconsin Supreme Court · 1979
- Allen & O'Hara, Inc. v. Barrett Wrecking, Inc.Court of Appeals for the Seventh Circuit · 1990
- Krause v. Milwaukee Mutual InsuranceWisconsin Supreme Court · 1969
5 more not listed; retrieve them via the Exa API.