Wood v. United States

Supreme Court of the United States

Decided February 27, 1922No. 100PublishedCited by 23 opinions

APPEAL FROM THE COURT OF CLAIMS. Appeal from a judgment of the Court of Claims rejecting a claim for damages arising from suspension of work under claimants’ contract.

1Opinion of the Court

Mr. Justice Brandéis

delivered the opinion of the court.

• The Philadelphia Steam Heating Company made a contract with the United States, approved April 5, 1897, .to furnish and install the boiler plant, heating system and other apparatus for the post-office building at Washington then under construction. The price fixed was $111,373; the time for completion 250 working days; with a forfeiture of $100 a day for each day’s delay. The contract provided that for each day’s delay “ in the execution of the work ” caused “ through any fault ” of the Govern ment one additional day was to be allowed…

2Cases cited1 opinion

  1. Wells Brothers Co. of NY v. United StatesSupreme Court of the United States · 1920

3Cited by23 opinions

  1. George A. Fuller Co. v. United StatesUnited States Court of Claims · 1947
  2. Charles I. Hosmer, Inc. v. CommonwealthMassachusetts Supreme Judicial Court · 1939
  3. H. E. Crook Co. v. United StatesSupreme Court of the United States · 1926
  4. Psaty & Fuhrman, Inc. v. Housing AuthoritySupreme Court of Rhode Island · 1949
  5. Kehm Corp. v. United StatesUnited States Court of Claims · 1950

18 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API