Manett-Seastrunk v. Terminal Bldg. Corp. of Dallas
Court of Appeals of Texas
1Opinion of the Court
Appellants entered into a written contract with appellee to do the electrical work on what is known as the Terminal Building in Dallas, for an agreed price of $78,645.50. Said contract provided that appellee would pay appellants on the 1st and 15th of each month 90 per cent. of the value of the work done and material placed on the ground, upon certificates issued by the architect. The contract further provided that appellee could order extra work done or make any changes in the original plans and specifications, and provided that the value of such extra work, where not agreed upon, should be…
2Cases cited2 opinions
- Saner-Whiteman Lumber Co. v. Texas & N. O. Ry. Co.Texas Commission of Appeals · 1926
- Community of Priests of St. Basil v. ByrneCourt of Appeals of Texas · 1921
3Cited by1 opinion
- Manett, Seastrunk & Buckner v. Terminal Building Corp.Texas Supreme Court · 1931