United States v. Wyckoff Pipe & Creosoting Co.
Supreme Court of the United States
1Opinion of the Court
Mr. Justice Brandéis
delivered the opinion ■ of the Court.
The Wyckoff Pipe & Creosoting Co., Inc., contracted with the United States, in December, 1917, to lay creosotad wood block floors in Navy Yard buildings at Nor-' folk, Virginia, furnishing all necessary labor and materials. On a part of the job the contractor was to begin the work immediately after delivery of a copy of the contract. This part was to be completed within 30 days thereafter. On other parts, work was to be deferred until such time as the Government was ready to proceed. These parts were to be finished within 43 days from…
2Cases cited3 opinions
- Alpha Portland Cement Co. v. MassachusettsSupreme Court of the United States · 1925
- Ripley v. United StatesSupreme Court of the United States · 1912
- United States v. MuellerSupreme Court of the United States · 1885
3Cited by14 opinions
- George A. Fuller Co. v. United StatesUnited States Court of Claims · 1947
- Kehm Corp. v. United StatesUnited States Court of Claims · 1950
- United States v. Burton Coal Co.Supreme Court of the United States · 1927
- Gulf States Creosoting Co. v. LovingCourt of Appeals for the Fourth Circuit · 1941
- Gee v. PayneMissouri Court of Appeals · 1997
9 more not listed; retrieve them via the Exa API.