1Opinion of the Court

WHITAKER, Judge.

Plaintiffs sue to recover extra costs incurred due to a suspension of the work for 69 days during which a change in the plans and specifications was being considered. It is stipulated that they are entitled to recover $8,727.44 on this account.

They also sue to recover for increased wages which they were required to pay common laborers, carpenters, cement finishers, and hoisting engineers.

Plaintiffs had a contract for the construction of the foundations of the Jane Addams Houses in Chicago. It was a relief project; it was intended to relieve unemployment, to provide a living…

2Cases cited15 opinions

  1. Red Cross Line v. Atlantic Fruit Co.Supreme Court of the United States · 1924
  2. Martin's Administrator v. Baltimore & Ohio RailroadSupreme Court of the United States · 1894
  3. Home Ins. Co. v. MorseSupreme Court of the United States · 1874
  4. Kihlberg v. United StatesSupreme Court of the United States · 1878
  5. Martinsburg & Potomac Railroad v. MarchSupreme Court of the United States · 1885

10 more not listed; retrieve them via the Exa API.

3Cited by26 opinions

  1. Sunswick Corporation v. United StatesUnited States Court of Claims · 1948
  2. United States v. BeuttasSupreme Court of the United States · 1945
  3. Bateson-Stolte, Inc. v. The United StatesUnited States Court of Claims · 1962
  4. Utah Construction & Mining Co. v. United StatesUnited States Court of Claims · 1964
  5. York Engineering & Construction Co. v. United StatesUnited States Court of Claims · 1945

21 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API