SWEENEY, District Judge.
The plaintiff who is a subcontractor sued on his contract with the defendant, the John Bowen Co.
In addition to this right of action, the plaintiff could have had recourse to the performance bond furnished by the defendant and four sureties. No action was brought on this bond.
The defendant filed an answer and a counterclaim growing out of the contract on which the plaintiff sued. The plaintiff then filed a reply to the defendant’s counterclaim, and in it included a counterclaim of its own. This claimed relief under the performance bond and against the various sureties…
2Cases cited2 opinions
- Warren v. Indian Refining Co.District Court, N.D. Indiana · 1939
- Downey v. PalmerDistrict Court, S.D. New York · 1939
3Cited by5 opinions
- Joseph Bancroft & Sons Co. v. M. Lowenstein & Sons, Inc.District Court, D. Delaware · 1970
- Hilderbrand v. AndersonMissouri Court of Appeals · 1954
- Southeastern Industrial Tire Co. v. Duraprene Corp.District Court, E.D. Pennsylvania · 1976
- Rubewa Products Co. v. Watson's Quality Turkey Products, Inc.District of Columbia Court of Appeals · 1968
- Maison De Marchands Industrielle Ltee-Industrial Merchants, Ltd. v. New York Silicate Book Slate Co.District Court, S.D. New York · 1952