Vorrath v. Garrelts
Michigan Court of Appeals
1Opinion of the CourtR. B. Burns, P. J.
Plaintiff contractor agreed to construct a house according to plans submitted by defendant owner for the sum of $28,948.70. Numerous changes in the plans, all of which were suggested by the defendant, increased the total price by an *465additional $6,000. After requesting, but not receiving, the additional $6,000 for these plan changes the plaintiff ceased working on the defendant’s partially-completed house.
At trial level the plaintiff’s mechanic’s lien was upheld and foreclosed in the amount of $6,663.
Seeking to invalidate plaintiff’s lien the defendant argues that plaintiff’s…
2Cases cited8 opinions
- Wallich Lumber Co. v. GoldsMichigan Supreme Court · 1965
- Burman v. EwaldMichigan Supreme Court · 1916
- Lowrie & Webb Lumber Co. v. FergusonMichigan Supreme Court · 1945
- Grand River Lumber & Coal Co. v. GlennMichigan Supreme Court · 1926
- Halpin v. GarmanMichigan Supreme Court · 1916
3 more not listed; retrieve them via the Exa API.
3Cited by11 opinions
- Norcross Co. v. Turner-Fisher AssociatesMichigan Court of Appeals · 1987
- Spartan Asphalt Paving Co. v. Grand Ledge Mobile Home ParkMichigan Court of Appeals · 1976
- Spartan Asphalt Paving Co. v. Tri-Cities Construction, Inc.Michigan Court of Appeals · 1976
- Renshaw v. SamuelsMichigan Court of Appeals · 1982
- Vorrath v. GarreltsMichigan Court of Appeals · 1973
6 more not listed; retrieve them via the Exa API.