Legal Opinion

New Mexico Attorney General v. New Mexico Public Regulation Commission

New Mexico Supreme Court

Decided September 28, 2015No. Docket No. S-1-SC-34768PublishedCited by 3 opinions

1Opinion of the Court

OPINION

CHÁVEZ, Justice.

{1} The Public Regulation Commission (PRC) granted Southwestern Public Service Company’s (SPS) application to (1) include a prepaid pension asset in its rate base in order for SPS to earn a return on this asset, and (2) obtain a renewable energy cost rider to recover approximately $22 million of renewable energy procurement costs from those customers who do not have a legislatively imposed limit on their renewable energy costs (non-capped customers). The Attorney General appeals the PRC’s final order granting SPS’s application, arguing that the approved rates are unjust…

2Cases cited17 opinions

  1. City of Corpus Christi v. Public Utility Commission of TexasTexas Supreme Court · 2001
  2. Omega Satellite Products Company v. City of IndianapolisCourt of Appeals for the Seventh Circuit · 1982
  3. New Mexico Industrial Energy Consumers v. New Mexico Public Regulation CommissionNew Mexico Supreme Court · 2007
  4. Jersey Central Power & Light Company v. Federal Energy Regulatory Commission, Allegheny Electric Cooperative, Inc., IntervenorsCourt of Appeals for the D.C. Circuit · 1987
  5. Citizens Utility Board v. Illinois Commerce CommissionIllinois Supreme Court · 1995

12 more not listed; retrieve them via the Exa API.

3Cited by3 opinions

  1. Public Service Company of New Mexico v. New Mexico Public Regulation CommissionNew Mexico Supreme Court · 2019
  2. Public Serv. Co. of N.M. v. N.M. Pub. Regulation Comm'nNew Mexico Supreme Court · 2019
  3. N.M. Att'y. Gen. v. N.M. Pub. Regulation Comm'n.New Mexico Supreme Court · 2015

Showing a preview — retrieve the full document via the Exa API.