Midland Power Cooperative v. Federal Energy Regulatory Commission
Court of Appeals for the D.C. Circuit
1Opinion of the Court
Opinion for the Court filed by Senior Circuit Judge WILLIAMS.
WILLIAMS, Senior Circuit Judge:
The Federal Energy Regulatory Commission issued an order directing Midland Power Cooperative, an Iowa electric utility, to “reconnect” to a wind generator within its territory. Swecker v. Midland Power Cooperative, 137 FERC P 61200 (2011) (“Order”). It denied Midland’s petition for rehearing. Swecker v. Midland Power Cooperative, 142 FERC P 61207 (2013) (“Order on Rehearing”). Midland and joint petitioner National Rural Electric Cooperative Association (“NRECA”) seek review. The first question, and as…
2Cases cited12 opinions
- United States v. L. A. Tucker Truck Lines, Inc.Supreme Court of the United States · 1952
- United States National Bank v. Independent Insurance Agents of America, Inc.Supreme Court of the United States · 1993
- Federal Energy Regulatory Commission v. MississippiSupreme Court of the United States · 1982
- Doe, John v. Exxon Mobil CorpCourt of Appeals for the D.C. Circuit · 2007
- Industrial Cogenerators v. Federal Energy Regulatory Commission, Florida Power Corporation Florida Public Service Commission, IntervenorsCourt of Appeals for the D.C. Circuit · 1995
7 more not listed; retrieve them via the Exa API.
3Cited by19 opinions
- Felder v. USTACourt of Appeals for the Second Circuit · 2022
- Swecker v. Midland Power CooperativeDistrict Court, District of Columbia · 2017
- Portland General Electric Co. v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 2017
- (PC) Hudson v. PhillipsDistrict Court, E.D. California · 2025
- (PC) Lazar v. JonesDistrict Court, E.D. California · 2024
14 more not listed; retrieve them via the Exa API.