Bostwick Irrigation District v. United States
Court of Appeals for the Eighth Circuit
1Opinion of the Court
WOLLMAN, Circuit Judge.
Bostwick Irrigation District and Kansas-Bostwick Irrigation District No. 2 appeal the district court’s1 denial of their request for declaratory judgment, brought under 43 U.S.C. § 390uu, seeking to enjoin the Bureau of Reclamation of the Department of Interior (Bureau) from charging the Districts for expenses incurred by the Army Corps of Engineers (Corps) for operation and maintenance of the Harlan County Dam and Reservoir. We affirm.
The district court’s lengthy, thorough memorandum opinion recites fully the factual background that gave rise to this litigation. We will…
2Cases cited7 opinions
- Heckler v. Community Health Services of Crawford County, Inc.Supreme Court of the United States · 1984
- Guaranty Trust Co. v. United StatesSupreme Court of the United States · 1938
- Goodman v. McDonnell Douglas Corp.Court of Appeals for the Eighth Circuit · 1979
- ETSI Pipeline Project v. MissouriSupreme Court of the United States · 1988
- Missouri v. AndrewsCourt of Appeals for the Eighth Circuit · 1986
2 more not listed; retrieve them via the Exa API.
3Cited by5 opinions
- Sumner Peck Ranch, Inc. v. Bureau of ReclamationDistrict Court, E.D. California · 1993
- First Bank System, Inc. v. MartinDistrict Court, D. Minnesota · 1991
- SPARROWBoard of Immigration Appeals · 1994
- United States v. Sheyenne Tooling & Manufacturing Co.District Court, D. North Dakota · 1996
- Bostwick Irrigation District, and Kansas-Bostwick Irrigation District No. 2 v. United States of America, Bostwick Irrigation District, Kansas-Bostwick Irrigation District No. 2 v. United StatesCourt of Appeals for the Eighth Circuit · 1990