1Opinion of the CourtLeedom, J.
Respondents, building contractors, brought this action to recover a balance claimed to be owing on an oral agreement for the construction of appellants’ dwelling. As a part of their original cause of action, respondents sought to have a “Lien Waiver” reformed to eliminate therefrom language reciting that respondents had received payment in full for all labor and materials furnished in the construction. In an amended complaint the claim for the balance owing and the claim for reformation of the instrument were stated in separate causes of action. Appellants denied owing any sum whatsoever on…
2Cases cited6 opinions
- Medin v. BrookfieldSouth Dakota Supreme Court · 1938
- Jones v. JonesSouth Dakota Supreme Court · 1940
- Seubert v. SeubertSouth Dakota Supreme Court · 1941
- Greve v. BissonSouth Dakota Supreme Court · 1943
- Bunker v. Great Falls Manufacturing Co.Supreme Court of New Hampshire · 1929
1 more not listed; retrieve them via the Exa API.
3Cited by5 opinions
- Ratzlaff v. Seven Bar Flying Service, Inc.New Mexico Court of Appeals · 1982
- Maryland Casualty Co. v. DelzerSouth Dakota Supreme Court · 1979
- Sprenger v. SprengerNorth Dakota Supreme Court · 1966
- Carol A. MacY v. United StatesCourt of Appeals for the Third Circuit · 1977
- Profit Counselors, Inc. v. KnightSouth Dakota Supreme Court · 1966