D & P Equipment Corp. v. Harvey Construction Co.
Massachusetts Appeals Court
1Opinion of the Court
There was no error in the entry of summary judgment dismissing this action brought under G. L. c. 149, § 29 (as amended through St. 1972, c. 774, '§ 5), as to Harvey and the surety on Harvey’s bond, because of the plaintiff’s failure to bring the action within the one-year period prescribed by that section. In view of the almost identical language used by the Legislature to define that period in the second paragraph of § 29 (“within one year after the day on which such claimant last performed”) and the notice period in the third paragraph (“within sixty-five days after the day on which the…
2Cases cited18 opinions
- Community National Bank v. DawesMassachusetts Supreme Judicial Court · 1976
- Insurance Rating Board v. Commissioner of InsuranceMassachusetts Supreme Judicial Court · 1969
- John B. Deary, Inc. v. CraneMassachusetts Appeals Court · 1976
- Peerless Unit Ventilation Co. v. D'Amore Construction Co.Massachusetts Supreme Judicial Court · 1933
- Commonwealth Bank & Trust Co. v. PlotkinMassachusetts Supreme Judicial Court · 1976
13 more not listed; retrieve them via the Exa API.
3Cited by6 opinions
- Great Barrington Savings Bank v. GensMassachusetts Appeals Court · 1979
- Barboza v. Aetna Casualty & Surety Co.Massachusetts Appeals Court · 1984
- Houston v. GreenwaldMassachusetts Superior Court · 2000
- James W. Flett Construction Co. v. Sciaba Construction Corp.Massachusetts Superior Court · 1995
- Earth Tech Environment & Infrastructure, Inc. v. Perini/Kiewit/CashmanMassachusetts Superior Court · 2004