Northern State Construction Co. v. Banchero
Washington Supreme Court
1Per curiam
This appeal presents two problems: (1) The sufficiency of an application for a continuance, and (2) the finality of an award in arbitration.
Appellants, Edward and Edith Banchero, employed Oliver W. Olson, an architect, to plan and design a large supermarket building for them. Their agreement with him had a clause providing for arbitration of all disputes under the rules of the American Arbitration Association. The architect prepared plans and specifications, and a formal contract of construction was executed by the Bancheros and the respondent, Northern State Construction Company. This…
2Cases cited11 opinions
- State v. GriffithWashington Supreme Court · 1958
- Arbitration Puget Sound Bridge & Dredging Co. v. Lake Washington ShipyardsWashington Supreme Court · 1939
- MacKay v. MacKayWashington Supreme Court · 1959
- Puget Sound Bridge & Dredging Co. v. FryeWashington Supreme Court · 1927
- Wagner v. Peshastin Lumber Co.Washington Supreme Court · 1928
6 more not listed; retrieve them via the Exa API.
3Cited by56 opinions
- Barnett v. HicksWashington Supreme Court · 1992
- Davidson v. HensenWashington Supreme Court · 1998
- Davidson v. HensenWashington Supreme Court · 1998
- International Ass'n of Fire Fighters, Local 46 v. City of EverettWashington Supreme Court · 2002
- Boyd v. DavisWashington Supreme Court · 1995
51 more not listed; retrieve them via the Exa API.